This study developed a new methodology for expediting the cable-stayed bridge construction process using 3D laser scanning. The developed methodology can be applied to the cable-stayed bridge constructed by thermal expansion based key segment closing method, in case of hydraulic jack based setback procedure is impossible. In conventional thermal expansion based key segment closing method, the last regular segment install-measurement-key segment fabrication should be subsequently performed. However, the methodology developed in this study use 3D laser scanning to measure before installing the last regular segment and predict the dimension of the key segment, so that can perform installing last regular segment and key segment fabrication parallel. The methodology developed in this study was applied to Cheonsa Bridge in South Korea, reducing the construction time 10 days.
본 연구에서는 3차원 레이저 스캐닝을 이용해 사장교의 시공 기간을 단축할 수 있는 방법을 개발했다. 개발된 기술은 유압 잭을 이용한 set-back이 불가능해 열 팽창 기반의 키 세그먼트 폐합으로 시공하는 사장교를 대상으로 한다. 기존 열 팽창 기반 키 세그먼트 폐합에서는 최종 정규 세그먼트 설치-계측-키세그먼트 제작이 순차적으로 수행되어야 하지만, 본 연구에서는 3차원 레이저 스캐닝을 이용해 최종 정규 세그먼트 설치 전 세그먼트 사이의 3차원 형상을 획득하고, 세그먼트 간의 상대 변위를 사전에 계측, 키 세그먼트의 크기를 미리 예측해 키 세그먼트 제작과 세그먼트 설치를 동시에 병렬로 진행해 시공기간을 단축하는 방법을 개발했다. 본 연구에서 개발된 기술은 대한민국의 천사대교에 적용되어 검증을 수행했고, 10일의 시공기간 단축을 달성했다.