Preventive maintenance scheduling of thermal generating units occupies a significant place in power system operation and expansion planning. At the same time, it is a challenging problem of multi-objective type with conflicting objectives. Many previous researches argued about the importance of operating cost, while others about the system reliability as a criterion of goodness.
This thesis deals with the maintenance scheduling problem as a multi-criteria decision making (MCDM) problem. The problem is formulated as a 0-1 integer program and a solution method based on the branch-and-bound technique is developed. Some fathoming rules suitable for the proposed model are also developed.
Through a case study with real data, some implications were found. They are; (1) when a system is in the state of high reserve margin, the maintenance schedule must be focused on the cost minimization side, and (2) when the capacity of the system is insufficient, impoving the system reliability must be emphasized.
전력계통의 발전기 보수계획 문제는 단. 중기 계통운영 계획및 장기확장 계획에 있어 중요한 위치를 차지하고 있다. 이러한 문제 해결을 위한 기존의 연구들은 보수계획수립을 단순히 운영비 최소화나 계통 신뢰도 극대화 등의 단일 목적에 의하여 결정하는 것으로 되어왔다. 그러나 위의 두가지 목적은 서로상충 되는 것들이고, 따라서 보수계획 문제는 본질적으로 MCDM문제로 파악 되어 해결 되어야 함은 자명하다.
본 논문에서는 이 문제를 MCDM문제로 정의하고 두가지 목적을 모두 고려하여 모형화 하였다. 문제 해결 방법으로는 분지 한계법(Branch-and-Bound)을 택하고 또한 제안한 모형에 적합한 새로운 가지제거규칙 (Fathoming Rule)을 제안하였다. 한국의 실제 데이타를 이용하여 사례 연구를 한 결과, 다음과 같은 사실을 제증명 할 수 있었다.
(1) 계통의 용량이 클 경우, 비용 최소화에 중점을 두는 것이 의미가 있다.
(2) 계통의 용량이 작을 경우, 계통 신뢰도 극대화를 강조하는 것이 의미가 있다.